Tina River hydropower project clears technical requirements for main dam construction

By: James Galvez - Managing Editor November 25, 2026

The Tina River Hydropower Development Project has secured technical clearance for the construction methodology and concrete mix of its main dam, allowing engineering, procurement and construction contractor Hyundai Engineering Co. (HEC) to proceed with the next phase of construction.

The clearance followed a nine-day implementation support mission by the project's Concessional Financing Partners (CFPs), led by the World Bank, from Oct. 12 to 20, 2026.

The mission included representatives of the Asian Development Bank (ADB), Korea Eximbank's Economic Development Cooperation Fund (EDCF) and the Australian government through the Department of Foreign Affairs and Trade (DFAT), together with the project's Dam Safety Advisory Panel (DSAP), lenders' technical advisers and owner's engineer.

According to the project office, the October mission successfully cleared the methodology for constructing the dam and the roller-compacted concrete (RCC) mix, enabling HEC to begin the main dam construction works.

The technical review focused on preparations for the foundation of the main RCC dam and the stability and excavation of the right abutment, taking into account recommendations made during the financing partners' previous site visit in March 2026.

The review was part of a broader assessment of implementation progress and construction readiness, including coordination among the Solomon Islands government, project developers, contractors, technical advisers and financing institutions.

The mission began with a full-day technical inspection of the dam site, followed by an opening meeting at the Heritage Park Hotel in Honiara.

Participants included representatives of the Ministry of Mines, Energy and Rural Electrification (MMERE), the government-established project office, Solomon Power (SP), Tina Hydropower Ltd. (THL), HEC and their respective owner's engineer and lenders' technical advisers.

A further site inspection on the third day focused on the powerhouse and tunnel portal.

Project Manager Pradip Verma presented an overview of implementation progress during the preceding six months, followed by technical meetings with THL, HEC and Solomon Power.

Technical review of dam foundation and construction preparations

A major component of the mission involved discussions among the CFPs, DSAP, lenders' technical advisers and owner's engineer on the engineering preparations for the main dam.

These included the foundation construction area for the RCC dam and the stability and excavation works on the right abutment.

The technical teams reviewed progress against recommendations from the March 2026 mission, with particular attention to the engineering requirements for safely advancing the dam foundation works.

The mission also examined the cofferdam, including its construction and the conditions at the dam site, as well as the left and right abutments.

Other infrastructure inspected included the batching plant, which will supply concrete for dam construction, and the conveyor belt system being built to transport materials from the batching plant to the main dam site.

The project also conducted joint technical and environmental and social discussions covering reservoir preparation and the sourcing and transportation of aggregates.

These activities form part of the construction planning required to coordinate the delivery of materials, site preparation and the implementation of major civil works.

Further technical meetings reviewed observations from recent site inspections, with THL and HEC presenting their responses to design matters and other implementation issues.

Construction optimization and coordination

The mission also considered measures to optimize and accelerate construction, particularly in critical work areas.

Discussions focused on construction methodologies, implementation planning and ways to strengthen coordination among the contractor, project company, government agencies, technical advisers and financing partners.

The project said the review was intended to support safe, timely and well-managed implementation.

The October mission concluded with agreement on the next steps, including additional technical discussions, site verification and continued coordination among the participating organizations.

The project described the outcome as a significant milestone, with the technical clearance of the dam construction methodology and RCC mix allowing HEC to proceed with construction of the main dam.

Solomon Islands' first large-scale hydropower project

The Tina River Hydropower Development Project is Solomon Islands' first large-scale renewable energy development and a major component of the country's efforts to expand access to cleaner and more reliable electricity.

The project is intended to provide more affordable electricity, particularly for Honiara, while improving the availability of renewable energy for communities in the country.

It is being implemented by the Solomon Islands government through MMERE and the project office, in partnership with Solomon Power and Tina Hydropower Ltd.

The development is supported by a group of international financing institutions and development partners, including the World Bank, ADB, the Australian government, Korea Eximbank's EDCF, the Green Climate Fund and the Abu Dhabi Fund for Development.

The financing partnership brings together multilateral development banks, bilateral development partners and climate finance institutions to support the country's hydropower development.

The October implementation support mission was the second biennial mission conducted by the concessional financing partners. It provided an opportunity to assess construction progress, review technical requirements and coordinate the next stages of project implementation.

With the main dam construction methodology and RCC mix cleared, the project is moving into the next phase of its civil works, with continued technical oversight and coordination among its government, engineering and financing partners.